Once the system has been started up, all equipment and components installed on the shelter are checked for functionality, and the process/plant is functioning, it is time to begin the certification process. Each CEMS must be certified according to the appropriate permit and regulatory requirements.

Certification Support

Our Field Service team will assist with all certification testing in accordance with regulations like 40 CFR Parts 60, 75, and 98. This may include performing or assisting with quality assurance tests like a 40 CFR 60 Cylinder Gas Audit (CGA), a 40 CFR 75 linearity check, a 7-Day Calibration Error Drift Test, a 40 CFR 60 Response Time Test, a 40 CFR 75 cycle time test, and a Relative Accuracy Test Audit (RATA).

Our field service technicians arrive on-site and verify the system performance by performing an initial daily calibration check, interact with the RATA test team to resolve issues, check the analyzer responses, and verify the data collected by the DAHS computer. Our environmental team can help make sure that you are performing the appropriate QA tests within the required time frames. They can also prepare certification reports, review reports that have been written by 3rd parties, and assist with or enter data for electronic submittals in the ECMPS Client Tool and PADEP Greenport.

REGULATIONS & TESTS COVERED:

40 CFR Part 60
40 CFR Part 75
40 CFR Part 98
RATA (Relative Accuracy Test Audit)
CGA (Cylinder Gas Audit)
Linearity Check
Response/Cycle Time Test
7-Day Calibration Drift Test

Certification Packages

We have several levels of CEMS certification packages from certification assistance with various levels of assistance depending on the need of the plant to full CEMS certification.

Contact CiSCO to determine which level of service is right for you or customize a certification package for your facility.

CERTIFICATION INQUIRIES

certquery@ciscocems.com

303-790-1000

What's Included at Each Level

1 DAHS verification and documentation for inclusion in the final Certification report
2 Remote assistance generating CeDAR reports for RATA runs, CGAs/linearity checks, response/cycle time tests, and 7-day drift tests
1 On-site assistance with RATA testing
2 Review of raw RATA data on-site in real-time
3 Instruction on running CGAs/linearity checks and response/cycle time tests
4 On-site generation of CGA/linearity, response/cycle time, and 7-day drift test reports from CeDAR
1 Secure a mutually acceptable 3rd party RATA test team and review their RATA protocol
2 Create a Certification Protocol describing all tests to be performed
3 Provide hardcopy and electronic Certification Protocol for regulatory submittal
4 Perform CGA/linearity, response/cycle time, and 7-day drift tests; review the RATA test report
5 Create the Certification Report and provide hardcopy/electronic copies for regulatory submittal
6 Enter and submit certification data in the EPA ECMPS Client Tool
7 Revise and resubmit the 40CFR75 Monitoring Plan in ECMPS based on certification results
8 Track down any documents missing from the Monitoring Plan (e.g. Fuel Meter certification) for submittal with the Certification Report

Certification Services Levels

The following table provides an example of the different levels of service options. Contact CiSCO to determine which level of service is right for you or customize a certification package for your facility.

CiSCO CEMS Certification Services levels table Download the CiSCO CEMS Certification Service Table (PDF)

Once the CEMS has been certified, our field service team is also willing and able to maintain the CEMS with quarterly, semi-annual, or annual maintenance contracts. CiSCO will modify and maintain CEMS from other distributors as well. See additional Environmental Services.

Ready to Certify Your CEMS?

Contact CiSCO to determine which level of service is right for you.